Mobile Station

  • You cal fill CNG into a car from the tube trailer at any place if you have mobile station which gas pipe line and electricity are not necessary.
    It is 3(three) bank system in the mobile station and vehicles can be directly refueled from the tube trailer which was filled with 250bar at the mother station.
    As pressure drop during fillng, compressor recovers the pressure of the high bank cylinders. so, mobile station makes possible very efficient and quickly filling.
  • list
  • list

Specification

Tube Skid 200bar Type2 Cylinder(1,025L)x12Cyl.3 Bank System : High(2Cyl),Medium(3Cyl),Low(7Cyl)
Total Gas Capacity 258m3 x 12 bottle = 3,096m³
Compressor CNG Gas Engine + Mechanical Compressor(32kw)
Flow Rate Average.600m3/h
Gas Engine Consumption 11m3/hr,57m3/1 tube trailer
Discharging Amount 3,096m3X0.9=2,786m3(Efficiency:90%)
Discharging Time 5 Min/Passenger Vehicle
Discharging Capacity CNG Vehicle(60L, 15m3),185 Cars
Weight(kg) Skid 17,242
CNG Gas 2,633
Compressor Module 3,500
Chassis 5,410
Trailer Head 8,500
Total 37,285

Skid Length Item Tube Q'ty & Length Working Pressure (bar) Total Water Capacity (liter) Total Gas Capacity (CNG/m³)
32' TT12-1025/3-620 CNG2 12/9,000mm 200 14,160 3,575